The following videos are of the
Corwin Residence in
![]()
The Steel Rebar is being tied in the Tie Beam area that is part of the
form.
Video One – the North Half of the home
Video Two – The South Half of the home
![]()
Still Pictures
Click on thumbnails to Enlarge the picture
Information regarding the 'Time to Build' the walls
This home has twice as many windows as similar sized homes with the same length of walls which gives in more wall pieces, this home has 136 wall pieces ‘floor to ceiling’ panels, headers and sills.
(21 more than similar sized homes)
With a 3 man crew, this home took 15 working days.
With a 9 man crew this home will take 5 working days.